Operations Update August 30, 2019:
Dust Control: Crews will be spraying the second application of calcium chloride dust control starting September 3, 2019. Grading may be required to prepare the surface of the road (removing potholes, etc.) prior to the second application. Following the grading, it can take up to two days for the dust control to be applied.
Dunphy Road Project: To protect Kneehill County's road infrastructure along the Kneehill Creek, a creek bank stabilization project will begin September 3, 2019 on the Dunphy Road. (Rge Rd 21-1A) The road will remain open during construction.